Table 6: Comparison of Financial Performance Under Zero Tax vs 100 €/t CO2 Tax
Financial Metric
Scenario A (No Tax / Taxed)
Scenario B (No Tax / Taxed)
Scenario C (No Tax / Taxed)
Annual System Cost [B €/yr]
12.61 / 13.29
7.67 / 8.35
5.91 / 11.83
Total System NPV [B €]
-2.65 / -9.99
-2.23 / -9.56
+7.11 / -56.47
Project IRR (%)
9.56% / 8.78%
15.27% / 12.77%
17.54% / N/A*
Simple Payback Period [Years]
8.92 / 9.44
6.22 / 7.21
5.51 / N/A*
Pathway 1: Levelized Cost of Electricity (LCOE) Sankey Diagrams
Interactive cost-flow decomposition tracing CAPEX and OPEX by technology into total system cost and LCOE (€/MWh) for the electricity-only pathway — unlimited versus limited CO₂.
LCOE · Scenario A (Unlimited CO₂)
€36.90 / MWh
€1.98 B / yr · 53.7 TWh served
LCOE · Scenario B (Limited CO₂)
€58.94 / MWh
Zero-CO₂ carbon-limited grid
Green Premium
+€22.04 / MWh
B vs. A
Lowest-Cost Case
Scenario A
Unlimited CO₂ baseline
Use the tabs below to move between the unlimited-CO₂ (Scenario A) and limited-CO₂ (Scenario B) cost-flow diagrams.
Pathway 2: Net Levelized Cost of Hydrogen (Net LCOH) Sankey Diagrams
Interactive cost-flow decomposition tracing CAPEX, OPEX, and carbon liabilities into the net cost of exported hydrogen (€/kg H₂) for Green, Blue and Grey pathways — with and without a carbon tax.
Net LCOH · Green (A)
€4.89 / kg H₂
146.56 €/MWh (LHV)
Net LCOH · Blue (B)
€2.55 / kg H₂
76.59 €/MWh (LHV)
Net LCOH · Grey (C)
€2.13 / kg H₂
63.95 €/MWh (LHV)
Lowest Untaxed Net LCOH
Grey H₂ (C)
Blue is +€0.42 / kg
Untaxed baseline: no carbon price. Use the tabs below to move between the Green, Blue and Grey cost-flow diagrams, or open the side-by-side comparison.